May 24, 2017

Improvements to the City's waterline infrastructure will continue along the East Main Street corridor.  Additional information regarding this project can be found at: http://durhamnc.gov/3001/East-Main-Street-Waterline-Replacement.

Planned Road / Lane Closures will occur as follows:

  *   Week of 5/22:
     *   At the intersection of East Main Street and Fayetteville Street.
     *   East Main Street between S. Elizabeth / Commerce and Fayetteville streets.  On-street parking will be closed in the work area.
     *   Flaggers will be used to maintain traffic flow on East Main Street between Hood and Fayetteville streets.
     *   UPDATE - Westbound Ramseur Street between Hood Street and Fayetteville Street (see attached map).
  *   Week of 5/30:
     *   Lane shifts on East Main Street between Dillard Street and Fayetteville Street.
     *   Westbound Ramseur Street between Dillard Street and Fayetteville Street.
     *   Lane closures on S. Elizabeth and Hood streets between East Main Street and Ramseur Street.
  *   Week of 6/5:
     *   Lane shifts on East Main Street between Dillard Street and Fayetteville Street.
     *   Westbound Ramseur Street between Dillard Street and Fayetteville Street.
     *   Lane closures on S. Elizabeth and Hood streets between East Main Street and Ramseur Street.

Week of May 22, 2017:

  *   UPDATE - Stormwater improvements along Ramseur Street between Hood and Fayetteville streets will begin on Thursday (see attached map).

     *   Westbound traffic in Ramseur Street will be closed between Hood and Fayetteville streets.  Traffic control signs and markings will be used for a detour using East Main Street.

     *   On-street parking on Ramseur Street between Hood and Fayetteville streets will be closed to accommodate stormwater installation.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

  *   Waterline installation and testing in East Main Street between S. Elizabeth / Commerce and Fayetteville streets, including near the Fayetteville Street / East Main Street intersection, will continue.

     *   Lane shifts and closures will be required near the Fayetteville Street / East Main Street intersection.  Flaggers will be used to maintain traffic flow through the intersection.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

  *   Various sanitary sewer installations in S. Elizabeth and Hood streets between Ramseur and East Main streets will begin.

     *   Lane shifts and local detours will be used to maintain traffic near installation areas.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Monday May 27-29, 2017:

  *   No work will take place over the Memorial Day weekend.

Week of May 30, 2017:

  *   Stormwater improvements along Ramseur Street between Dillard and Fayetteville streets will continue.

     *   Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

  *   Final waterline and service connections on East Main Street between Dillard and Fayetteville streets will continue.
     *   Work includes preparing for final waterline connections at Commerce / East Main streets and Dillard / East Main streets.
     *   Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
     *   Through traffic on East Main Street will be maintained.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

  *   Various sanitary sewer installations in S. Elizabeth and Hood streets between Ramseur and East Main streets will continue.

     *   Lane shifts and local detours will be used to maintain traffic near installation areas.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Sunday June 3-4, 2017:

  *   Stormwater improvements along Ramseur Street between Dillard and Fayetteville streets will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Week of June 5, 2017:

  *   Stormwater improvements along Ramseur Street between Dillard and Fayetteville streets will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

  *   Final waterline and service connections on East Main Street between Dillard and Fayetteville streets will continue.
     *   Work includes preparing for final waterline connections at Commerce / East Main streets and Dillard / East Main streets.
     *   Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
     *   Through traffic on East Main Street will be maintained.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

  *   Various sanitary sewer installations in S. Elizabeth and Hood streets between Ramseur and East Main streets will continue.

     *   Lane shifts and local detours will be used to maintain traffic near installation areas.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Sunday June 10-11, 2017:

  *   Stormwater improvements along Ramseur Street between Dillard and Fayetteville streets will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Future Weeks:

  *   Restoration of sidewalks and other surfaces impacted by the project will continue.
  *   Stormwater improvements along Ramseur and East Main Street will continue.
  *   Following the completion of waterline and stormwater installation at Fayetteville / East Main streets, pavement improvements will take place in the intersection.
  *   Work will exceed the current City noise ordinance.
  *   Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<http://www.DurhamOperationGreenlight.org>.  Find more information about all of the department's current projects at www.DurhamWaterProjects.org<http://www.DurhamWaterProjects.org>.  If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170524/55cffee1/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 2734 bytes
Desc: image001.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170524/55cffee1/attachment-0002.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 23964 bytes
Desc: image002.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170524/55cffee1/attachment-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: American Tobacco Ramseur St Westbound Detour 11x17 2017_05_24.jpg
Type: image/jpeg
Size: 2055063 bytes
Desc: American Tobacco Ramseur St Westbound Detour 11x17 2017_05_24.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170524/55cffee1/attachment-0003.jpg>


More information about the INC-list mailing list