[Durham INC] East Main Street Waterline Replacement Project Update | 5-24-17
Butts, Kirk
Kirk.Butts at durhamnc.gov
Wed May 24 15:17:32 EDT 2017
[cid:image001.jpg at 01D087F9.E3A39760][cid:image002.png at 01D087F9.E3A39760]
East Main Street Waterline Replacement Project Update and Two-Week Look Ahead
May 24, 2017
Improvements to the City's waterline infrastructure will continue along the East Main Street corridor. Additional information regarding this project can be found at: http://durhamnc.gov/3001/East-Main-Street-Waterline-Replacement.
Planned Road / Lane Closures will occur as follows:
* Week of 5/22:
* At the intersection of East Main Street and Fayetteville Street.
* East Main Street between S. Elizabeth / Commerce and Fayetteville streets. On-street parking will be closed in the work area.
* Flaggers will be used to maintain traffic flow on East Main Street between Hood and Fayetteville streets.
* UPDATE - Westbound Ramseur Street between Hood Street and Fayetteville Street (see attached map).
* Week of 5/30:
* Lane shifts on East Main Street between Dillard Street and Fayetteville Street.
* Westbound Ramseur Street between Dillard Street and Fayetteville Street.
* Lane closures on S. Elizabeth and Hood streets between East Main Street and Ramseur Street.
* Week of 6/5:
* Lane shifts on East Main Street between Dillard Street and Fayetteville Street.
* Westbound Ramseur Street between Dillard Street and Fayetteville Street.
* Lane closures on S. Elizabeth and Hood streets between East Main Street and Ramseur Street.
Week of May 22, 2017:
* UPDATE - Stormwater improvements along Ramseur Street between Hood and Fayetteville streets will begin on Thursday (see attached map).
* Westbound traffic in Ramseur Street will be closed between Hood and Fayetteville streets. Traffic control signs and markings will be used for a detour using East Main Street.
* On-street parking on Ramseur Street between Hood and Fayetteville streets will be closed to accommodate stormwater installation.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Waterline installation and testing in East Main Street between S. Elizabeth / Commerce and Fayetteville streets, including near the Fayetteville Street / East Main Street intersection, will continue.
* Lane shifts and closures will be required near the Fayetteville Street / East Main Street intersection. Flaggers will be used to maintain traffic flow through the intersection.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Various sanitary sewer installations in S. Elizabeth and Hood streets between Ramseur and East Main streets will begin.
* Lane shifts and local detours will be used to maintain traffic near installation areas.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Saturday-Monday May 27-29, 2017:
* No work will take place over the Memorial Day weekend.
Week of May 30, 2017:
* Stormwater improvements along Ramseur Street between Dillard and Fayetteville streets will continue.
* Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Final waterline and service connections on East Main Street between Dillard and Fayetteville streets will continue.
* Work includes preparing for final waterline connections at Commerce / East Main streets and Dillard / East Main streets.
* Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
* Through traffic on East Main Street will be maintained.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Various sanitary sewer installations in S. Elizabeth and Hood streets between Ramseur and East Main streets will continue.
* Lane shifts and local detours will be used to maintain traffic near installation areas.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Saturday-Sunday June 3-4, 2017:
* Stormwater improvements along Ramseur Street between Dillard and Fayetteville streets will continue.
* Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Week of June 5, 2017:
* Stormwater improvements along Ramseur Street between Dillard and Fayetteville streets will continue.
* Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Final waterline and service connections on East Main Street between Dillard and Fayetteville streets will continue.
* Work includes preparing for final waterline connections at Commerce / East Main streets and Dillard / East Main streets.
* Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
* Through traffic on East Main Street will be maintained.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Various sanitary sewer installations in S. Elizabeth and Hood streets between Ramseur and East Main streets will continue.
* Lane shifts and local detours will be used to maintain traffic near installation areas.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Saturday-Sunday June 10-11, 2017:
* Stormwater improvements along Ramseur Street between Dillard and Fayetteville streets will continue.
* Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Future Weeks:
* Restoration of sidewalks and other surfaces impacted by the project will continue.
* Stormwater improvements along Ramseur and East Main Street will continue.
* Following the completion of waterline and stormwater installation at Fayetteville / East Main streets, pavement improvements will take place in the intersection.
* Work will exceed the current City noise ordinance.
* Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<http://www.DurhamOperationGreenlight.org>. Find more information about all of the department's current projects at www.DurhamWaterProjects.org<http://www.DurhamWaterProjects.org>. If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170524/55cffee1/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 2734 bytes
Desc: image001.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170524/55cffee1/attachment-0002.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 23964 bytes
Desc: image002.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170524/55cffee1/attachment-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: American Tobacco Ramseur St Westbound Detour 11x17 2017_05_24.jpg
Type: image/jpeg
Size: 2055063 bytes
Desc: American Tobacco Ramseur St Westbound Detour 11x17 2017_05_24.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170524/55cffee1/attachment-0003.jpg>
More information about the INC-list
mailing list