[Durham INC] East Main Street Waterline Replacement Project Update | 6-1-17

Butts, Kirk Kirk.Butts at durhamnc.gov
Thu Jun 1 12:07:23 EDT 2017


[cid:image001.jpg at 01D087F9.E3A39760][cid:image002.png at 01D087F9.E3A39760]

East Main Street Waterline Replacement Project Update and Two-Week Look Ahead

June 1, 2017

Improvements to the City's waterline infrastructure will continue along the East Main Street corridor.  Additional information regarding this project can be found at: http://durhamnc.gov/3001/East-Main-Street-Waterline-Replacement.

Planned Road / Lane Closures will occur as follows:

  *   Week of 6/5:
     *   Lane shifts on East Main Street between Dillard Street and Fayetteville Street.
     *   Westbound Ramseur Street between Dillard Street and Fayetteville Street.
     *   Lane closures on South Elizabeth and Hood streets between East Main Street and Ramseur Street.
  *   Week of 6/12:
     *   Lane shifts on East Main Street between Dillard Street and Fayetteville Street.
     *   Westbound Ramseur Street between Dillard Street and Fayetteville Street.
     *   Lane closures on Hood Street between East Main Street and Ramseur Street.

Saturday-Sunday June 3-4, 2017:

  *   No work is planned.

Week of June 5, 2017:

  *   Stormwater and waterline installation along Ramseur Street between Dillard and Fayetteville streets will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

  *   Final waterline and service connections on East Main Street between Dillard and Fayetteville streets will continue.
     *   Work includes preparing for final waterline connections at Commerce / East Main streets and Dillard / East Main streets.
     *   Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
     *   Through traffic on East Main Street will be maintained.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

  *   Various sanitary sewer installations in S. Elizabeth and Hood streets between Ramseur and East Main streets will continue.

     *   Lane shifts and local detours will be used to maintain traffic near installation areas.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Sunday June 10-11, 2017:

  *   Stormwater and waterline installation along Ramseur Street between Dillard and Fayetteville streets will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Week of June 12, 2017:

  *   Stormwater and waterline installation along Ramseur Street between Dillard and Fayetteville streets will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

  *   Final waterline and service connections on East Main Street between Dillard and Fayetteville streets will continue.
     *   Work includes preparing for final waterline connections at Commerce / East Main streets and Dillard / East Main streets.
     *   Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
     *   Through traffic on East Main Street will be maintained.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

  *   Various sanitary sewer installations in Hood Street between Ramseur and East Main streets will continue.

     *   Lane shifts and local detours will be used to maintain traffic near installation areas.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Sunday June 17-18, 2017:

  *   Stormwater and waterline installation along Ramseur Street between Dillard and Fayetteville streets will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Future Weeks:

  *   Restoration of sidewalks and other surfaces impacted by the project will continue.
  *   Stormwater improvements along Ramseur and East Main Street will continue.
  *   Following the completion of waterline and stormwater installation at Fayetteville / East Main streets, pavement improvements will take place in the intersection.
  *   Work will exceed the current City noise ordinance.
  *   Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<http://www.DurhamOperationGreenlight.org>.  Find more information about all of the department's current projects at www.DurhamWaterProjects.org<http://www.DurhamWaterProjects.org>.  If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170601/e8edff7a/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 2734 bytes
Desc: image001.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170601/e8edff7a/attachment-0002.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 23964 bytes
Desc: image002.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170601/e8edff7a/attachment-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: American Tobacco Ramseur St Westbound Detour 11x17 2017_05_24.jpg
Type: image/jpeg
Size: 2055063 bytes
Desc: American Tobacco Ramseur St Westbound Detour 11x17 2017_05_24.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170601/e8edff7a/attachment-0003.jpg>


More information about the INC-list mailing list