[Durham INC] East Main Street Waterline Replacement Project Update | 6-1-17
Butts, Kirk
Kirk.Butts at durhamnc.gov
Thu Jun 1 12:07:23 EDT 2017
[cid:image001.jpg at 01D087F9.E3A39760][cid:image002.png at 01D087F9.E3A39760]
East Main Street Waterline Replacement Project Update and Two-Week Look Ahead
June 1, 2017
Improvements to the City's waterline infrastructure will continue along the East Main Street corridor. Additional information regarding this project can be found at: http://durhamnc.gov/3001/East-Main-Street-Waterline-Replacement.
Planned Road / Lane Closures will occur as follows:
* Week of 6/5:
* Lane shifts on East Main Street between Dillard Street and Fayetteville Street.
* Westbound Ramseur Street between Dillard Street and Fayetteville Street.
* Lane closures on South Elizabeth and Hood streets between East Main Street and Ramseur Street.
* Week of 6/12:
* Lane shifts on East Main Street between Dillard Street and Fayetteville Street.
* Westbound Ramseur Street between Dillard Street and Fayetteville Street.
* Lane closures on Hood Street between East Main Street and Ramseur Street.
Saturday-Sunday June 3-4, 2017:
* No work is planned.
Week of June 5, 2017:
* Stormwater and waterline installation along Ramseur Street between Dillard and Fayetteville streets will continue.
* Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Final waterline and service connections on East Main Street between Dillard and Fayetteville streets will continue.
* Work includes preparing for final waterline connections at Commerce / East Main streets and Dillard / East Main streets.
* Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
* Through traffic on East Main Street will be maintained.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Various sanitary sewer installations in S. Elizabeth and Hood streets between Ramseur and East Main streets will continue.
* Lane shifts and local detours will be used to maintain traffic near installation areas.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Saturday-Sunday June 10-11, 2017:
* Stormwater and waterline installation along Ramseur Street between Dillard and Fayetteville streets will continue.
* Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Week of June 12, 2017:
* Stormwater and waterline installation along Ramseur Street between Dillard and Fayetteville streets will continue.
* Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Final waterline and service connections on East Main Street between Dillard and Fayetteville streets will continue.
* Work includes preparing for final waterline connections at Commerce / East Main streets and Dillard / East Main streets.
* Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
* Through traffic on East Main Street will be maintained.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Various sanitary sewer installations in Hood Street between Ramseur and East Main streets will continue.
* Lane shifts and local detours will be used to maintain traffic near installation areas.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Saturday-Sunday June 17-18, 2017:
* Stormwater and waterline installation along Ramseur Street between Dillard and Fayetteville streets will continue.
* Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Future Weeks:
* Restoration of sidewalks and other surfaces impacted by the project will continue.
* Stormwater improvements along Ramseur and East Main Street will continue.
* Following the completion of waterline and stormwater installation at Fayetteville / East Main streets, pavement improvements will take place in the intersection.
* Work will exceed the current City noise ordinance.
* Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<http://www.DurhamOperationGreenlight.org>. Find more information about all of the department's current projects at www.DurhamWaterProjects.org<http://www.DurhamWaterProjects.org>. If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170601/e8edff7a/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 2734 bytes
Desc: image001.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170601/e8edff7a/attachment-0002.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 23964 bytes
Desc: image002.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170601/e8edff7a/attachment-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: American Tobacco Ramseur St Westbound Detour 11x17 2017_05_24.jpg
Type: image/jpeg
Size: 2055063 bytes
Desc: American Tobacco Ramseur St Westbound Detour 11x17 2017_05_24.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170601/e8edff7a/attachment-0003.jpg>
More information about the INC-list
mailing list