Improvements to the City's waterline infrastructure will continue along the East Main Street corridor.  Additional information regarding this project can be found at: http://durhamnc.gov/3001/East-Main-Street-Waterline-Replacement.

Planned Road / Lane Closures will occur as follows:

  *   Week of 6/26:
     *   Lane shifts and flaggers on East Main Street between Dillard Street and Fayetteville Street.
     *   Lane closures on Ramseur Street between Hood Street and Fayetteville Street.
  *   Week of 7/3:
     *   Lane shifts and flaggers on East Main Street between Roxboro Street and Fayetteville Street.
     *   Lane closures on Ramseur Street between Dillard Street and Fayetteville Street.

Saturday-Sunday June 24-25, 2017:

  *   No work is planned.

Week of June 26, 2017:

  *   Final waterline and service connections on East Main Street between Dillard and Fayetteville streets will continue.
     *   Work includes final waterline connections at Dillard / East Main streets.
     *   Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
     *   Waterline service reconnections will be coordinated with affected parties at least seven days in advance of interruption.
     *   Through traffic on East Main Street will be maintained.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.
  *   Waterline and service installations along Ramseur Street between Hood and Fayetteville streets will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at waterline crossing locations.
     *   Waterline service reconnections will be coordinated with affected parties at least seven days in advance of interruption.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Sunday July 1-2, 2017:

  *   Waterline abandonment on East Main Street between Roxboro and Fayetteville streets will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
     *   Through traffic on East Main Street will be maintained.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Week of July 3, 2017:

  *   No work will take place on July 4th.
  *   Existing waterline abandonment on East Main Street between Roxboro and Fayetteville streets will take place.
     *   Isolated lane shifts and flaggers will be used to maintain traffic at abandonment locations on East Main Street.
     *   Through traffic on East Main Street will be maintained.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.
  *   Waterline and service installations along Ramseur Street between Hood and Fayetteville streets will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at waterline crossing locations.
     *   Waterline service reconnections will be coordinated with affected parties at least seven days in advance of interruption.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

  *   Stormwater installation along Ramseur Street between Dillard and Hood streets will continue.
     *   Lane closures and detours will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Sunday July 8-9, 2017:

  *   Waterline abandonment on East Main Street between Roxboro and Fayetteville streets will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
     *   Through traffic on East Main Street will be maintained.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Future Weeks:

  *   Restoration of sidewalks and other surfaces impacted by the project will continue.
  *   Waterline service reconnections in Angier Avenue between East Main Street and Elm Avenue will coordinated with affected residents.
  *   Stormwater improvements along East Main Street will continue.
  *   Pavement improvements in the intersection of Fayetteville / East Main street are anticipated to occur in late July.  An intersection closure with traffic detours is planned for approximately 4-5 days to complete the work.
  *   Work will exceed the current City noise ordinance.
  *   Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<http://www.DurhamOperationGreenlight.org>.  Find more information about all of the department's current projects at www.DurhamWaterProjects.org<http://www.DurhamWaterProjects.org>.  If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170622/e8013680/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 2734 bytes
Desc: image001.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170622/e8013680/attachment.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 23964 bytes
Desc: image002.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170622/e8013680/attachment.png>


More information about the INC-list mailing list