[Durham INC] East Main Street Waterline Replacement Project Update | 6-22-17
Butts, Kirk
Kirk.Butts at durhamnc.gov
Thu Jun 22 14:52:24 EDT 2017
[cid:image001.jpg at 01D087F9.E3A39760][cid:image002.png at 01D087F9.E3A39760]
East Main Street Waterline Replacement Project Update and Two-Week Look Ahead
June 22, 2017
Improvements to the City's waterline infrastructure will continue along the East Main Street corridor. Additional information regarding this project can be found at: http://durhamnc.gov/3001/East-Main-Street-Waterline-Replacement.
Planned Road / Lane Closures will occur as follows:
* Week of 6/26:
* Lane shifts and flaggers on East Main Street between Dillard Street and Fayetteville Street.
* Lane closures on Ramseur Street between Hood Street and Fayetteville Street.
* Week of 7/3:
* Lane shifts and flaggers on East Main Street between Roxboro Street and Fayetteville Street.
* Lane closures on Ramseur Street between Dillard Street and Fayetteville Street.
Saturday-Sunday June 24-25, 2017:
* No work is planned.
Week of June 26, 2017:
* Final waterline and service connections on East Main Street between Dillard and Fayetteville streets will continue.
* Work includes final waterline connections at Dillard / East Main streets.
* Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
* Waterline service reconnections will be coordinated with affected parties at least seven days in advance of interruption.
* Through traffic on East Main Street will be maintained.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Waterline and service installations along Ramseur Street between Hood and Fayetteville streets will continue.
* Lane shifts and flaggers will be used to maintain traffic at waterline crossing locations.
* Waterline service reconnections will be coordinated with affected parties at least seven days in advance of interruption.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Saturday-Sunday July 1-2, 2017:
* Waterline abandonment on East Main Street between Roxboro and Fayetteville streets will continue.
* Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
* Through traffic on East Main Street will be maintained.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Week of July 3, 2017:
* No work will take place on July 4th.
* Existing waterline abandonment on East Main Street between Roxboro and Fayetteville streets will take place.
* Isolated lane shifts and flaggers will be used to maintain traffic at abandonment locations on East Main Street.
* Through traffic on East Main Street will be maintained.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Waterline and service installations along Ramseur Street between Hood and Fayetteville streets will continue.
* Lane shifts and flaggers will be used to maintain traffic at waterline crossing locations.
* Waterline service reconnections will be coordinated with affected parties at least seven days in advance of interruption.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Stormwater installation along Ramseur Street between Dillard and Hood streets will continue.
* Lane closures and detours will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Saturday-Sunday July 8-9, 2017:
* Waterline abandonment on East Main Street between Roxboro and Fayetteville streets will continue.
* Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
* Through traffic on East Main Street will be maintained.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Future Weeks:
* Restoration of sidewalks and other surfaces impacted by the project will continue.
* Waterline service reconnections in Angier Avenue between East Main Street and Elm Avenue will coordinated with affected residents.
* Stormwater improvements along East Main Street will continue.
* Pavement improvements in the intersection of Fayetteville / East Main street are anticipated to occur in late July. An intersection closure with traffic detours is planned for approximately 4-5 days to complete the work.
* Work will exceed the current City noise ordinance.
* Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<http://www.DurhamOperationGreenlight.org>. Find more information about all of the department's current projects at www.DurhamWaterProjects.org<http://www.DurhamWaterProjects.org>. If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170622/e8013680/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 2734 bytes
Desc: image001.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170622/e8013680/attachment.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 23964 bytes
Desc: image002.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170622/e8013680/attachment.png>
More information about the INC-list
mailing list