[Durham INC] East Main Street Waterline Replacement Project Update | 9-14-17

Butts, Kirk Kirk.Butts at durhamnc.gov
Thu Sep 14 16:15:37 EDT 2017


[cid:image004.png at 01D32274.2C04A910][cid:image002.png at 01D087F9.E3A39760]

East Main Street Waterline Replacement Project Update and Two-Week Look Ahead

September 14, 2017

Improvements to the City's waterline infrastructure will continue along the East Main Street corridor.  Additional information regarding this project can be found at: http://durhamnc.gov/3001/East-Main-Street-Waterline-Replacement.

Planned Road / Lane Closures will occur as follows:

  *   Week of 9/18:
     *   Lane shifts and flaggers on East Main Street between Roxboro Street and Fayetteville Street, Hood Street, South Elizabeth Street, and Ramseur Street.
  *   Week of 9/25:
     *   Lane shifts and flaggers on East Main Street between Roxboro Street and Fayetteville Street, Hood Street, South Elizabeth Street, and Ramseur Street.

Week of September 18, 2017:

  *   Sidewalk/curb replacements and abandonment of existing waterlines in East Main Street between Roxboro and Fayetteville streets, Hood Street, South Elizabeth Street, and Ramseur Street will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at isolated locations in the project area.
     *   Through traffic on East Main Street will be maintained.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Sunday September 23-24, 2017:

  *   No work is planned for Saturday, September 23rd or Sunday, September 24th.

Week of September 25, 2017:

  *   Sidewalk/curb replacements and abandonment of existing waterlines in East Main Street between Roxboro and Fayetteville streets, Hood Street, South Elizabeth Street, and Ramseur Street will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at isolated locations in the project area.
     *   Through traffic on East Main Street will be maintained.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Sunday September 30 - October 1, 2017:

  *   No work is planned for Saturday, September 30th or Sunday, October 1st.

Future Weeks:

  *   Restoration of sidewalks and other surfaces impacted by the project will continue.
  *   Work will exceed the current City noise ordinance.
  *   Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<http://www.DurhamOperationGreenlight.org>.  Find more information about all of the department's current projects at www.DurhamWaterProjects.org<http://www.DurhamWaterProjects.org>.  If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170914/2bb8787d/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 4710 bytes
Desc: image001.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170914/2bb8787d/attachment.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 23964 bytes
Desc: image002.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170914/2bb8787d/attachment-0001.png>


More information about the INC-list mailing list