[Durham INC] Central Park Waterline Replacement Project Update | 9-20-18

Butts, Kirk Kirk.Butts at durhamnc.gov
Thu Sep 20 15:56:54 EDT 2018


[cid:image001.png at 01D450FA.48F26C00]

Central Park Waterline Replacement Project Update and Two-Week Look Ahead

September 20, 2018

The City appreciates your ongoing patience with the work along the busy corridors associated with the Central Park Waterline Replacement Project.  Additional information regarding this project can be found at: http://durhamnc.gov/1251/Durham-Central-Park-Waterline-Replacement.

Planned Road / Lane Closures will occur as follows:


  *   Week of 9/24:
     *   Mangum Street will be reduced to one lane between Corporation Street and West Morgan Street.
     *   Corporation Street will be reduced to one lane between Rigsbee Avenue and Mangum Street.
     *   Corporation Street between North Duke and Mangum Street, Mangum Street between Corporation Street and Morgan Street, and Hunt Street between Mangum Street and Rigsbee Avenue may be closed temporarily for repaving as equipment becomes available.


  *   Week of 10/1:
     *   Mangum Street will be reduced to one lane between Corporation Street and West Morgan Street.
     *   Corporation Street will be reduced to one lane between Rigsbee Avenue and Mangum Street.
     *   Corporation Street between North Duke and Mangum Street, Mangum Street between Corporation Street and Morgan Street, and Hunt Street between Mangum Street and Rigsbee Avenue may be closed temporarily for repaving as equipment becomes available.

Week of September 24, 2018:


  *   Mangum Street will be reduced to one lane between Corporation Street and West Morgan Street as water services are connected to the new water line.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Flaggers will be utilized for traffic control.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Periodic one-lane interruptions will occur on Corporation Street between N. Duke Street and Mangum Street as water services are connected to the new water line.

     *   Flaggers will be utilized for traffic control.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.

Saturday - Sunday September 29-30, 2018:

     *   No work planned.

Week of October 1, 2018:


  *   Mangum Street will be reduced to one lane between Corporation Street and West Morgan Street as water services are connected to the new water line.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Flaggers will be utilized for traffic control.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Periodic one-lane interruptions will occur on Corporation Street between N. Duke Street and Mangum Street as water services are connected to the new water line.

     *   Flaggers will be utilized for traffic control.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.

Saturday - Sunday October 6-7, 2018:

     *   No work planned.

Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.durhamoperationgreenlight.org_&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=P9cuE7s58z3AiHwHk-252uyd7ISyrXIibBEhpubjVjI&e=>.  Find more information about all of the department's current projects at www.DurhamWaterProjects.org<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.durhamwaterprojects.org_&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=a_TY6hAafgEez5UiOC9Jftqc8r7uKu_HvyBR48S1r2Y&e=>.  If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20180920/d56075eb/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 9001 bytes
Desc: image001.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20180920/d56075eb/attachment.png>


More information about the INC-list mailing list