[Durham INC] Central Park Waterline Replacement Project Update | 6-29-17

Butts, Kirk Kirk.Butts at durhamnc.gov
Thu Jun 29 15:24:56 EDT 2017


[cid:image001.jpg at 01D087F9.E3A39760][cid:image002.png at 01D087F9.E3A39760]

Central Park Waterline Replacement Project Update and Two-Week Look Ahead

June 29, 2017

The City appreciates your ongoing patience with the work along the busy corridors associated with the Central Park Waterline Replacement Project.  Additional information regarding this project can be found at: http://durhamnc.gov/1251/Durham-Central-Park-Waterline-Replacemen<https://urldefense.proofpoint.com/v2/url?u=http-3A__durhamnc.gov_1251_Durham-2DCentral-2DPark-2DWaterline-2DReplacemen&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=Rb7nKBS3Bw_Yr-O03vyV2P3Q7IQjZpIH9dPvjCkPz_c&e=>.

Planned Road / Lane Closures will occur as follows:

  *   Week of 7/3:
     *   Eastbound lane closed on Fernway Avenue between Morris Street and Fuller Street.
     *   Southbound lane closed at intersection of Fernway Avenue and Morris Street.
  *   Week of 7/10:
     *   Eastbound lane closed on Fernway Avenue between Morris Street and Fuller Street.

Week of July 3, 2017:

  *   No work will take place on July 4th.
  *   Fernway Avenue will be reduced to one lane as waterline installation begins starting at Morris Street.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Flaggers will be utilized for traffic control.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.
  *   Intersection of Fernway Avenue and Morris Street will be reduced to one lane while existing waterline is tapped.
     *   Traffic control signs and markings will be used for all traffic detours.
     *   Flaggers will be utilized for traffic control.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

Saturday - Sunday July 8-9, 2017:

  *   No work planned.  Fernway Avenue will be reduced to one lane.

Week of July 10, 2017:

  *   Fernway Avenue will be reduced to one lane as waterline installation continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Flaggers will be utilized for traffic control.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

Saturday - Sunday July 15-16, 2017:

  *   No work planned.  Fernway Avenue will be reduced to one lane.

Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.durhamoperationgreenlight.org_&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=P9cuE7s58z3AiHwHk-252uyd7ISyrXIibBEhpubjVjI&e=>.  Find more information about all of the department's current projects at www.DurhamWaterProjects.org<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.durhamwaterprojects.org_&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=a_TY6hAafgEez5UiOC9Jftqc8r7uKu_HvyBR48S1r2Y&e=>.  If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170629/2905eba1/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 2734 bytes
Desc: image001.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170629/2905eba1/attachment.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 23964 bytes
Desc: image002.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170629/2905eba1/attachment.png>


More information about the INC-list mailing list