[Durham INC] Central Park Waterline Replacement Project Update | 7-14-17

Butts, Kirk Kirk.Butts at durhamnc.gov
Fri Jul 14 08:44:00 EDT 2017


[cid:image001.jpg at 01D087F9.E3A39760][cid:image002.png at 01D087F9.E3A39760]

Central Park Waterline Replacement Project Update and Two-Week Look Ahead

July 14, 2017

The City appreciates your ongoing patience with the work along the busy corridors associated with the Central Park Waterline Replacement Project.  Additional information regarding this project can be found at: http://durhamnc.gov/1251/Durham-Central-Park-Waterline-Replacemen<https://urldefense.proofpoint.com/v2/url?u=http-3A__durhamnc.gov_1251_Durham-2DCentral-2DPark-2DWaterline-2DReplacemen&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=Rb7nKBS3Bw_Yr-O03vyV2P3Q7IQjZpIH9dPvjCkPz_c&e=>.

Planned Road / Lane Closures will occur as follows:

  *   Week of 7/17:
     *   Fernway Avenue eastbound lane will be closed between Fuller Street and Morris Street.
     *   Fuller Street will be closed to all traffic between Fernway Avenue and Corporation Street.
     *   Corporation Street westbound lane will be closed between Morris Street and Fuller Street.
  *   Week of 7/24:
     *   Fuller Street will be closed to all traffic between Fernway Avenue and Corporation Street.
     *   Corporation Street westbound lane will be closed between Morris Street and Fuller Street.

Week of July 17, 2017:

  *   Fernway Avenue will be reduced to one lane as waterline installation continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Flaggers will be utilized for traffic control.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Corporation Street will be reduced to one lane as waterline installation begins.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Flaggers will be utilized for traffic control.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Fuller Street will be reduced to one lane as waterline installation begins.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Flaggers will be utilized for traffic control.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

Saturday - Sunday July 22-23, 2017:

  *   No work planned. Corporation Street will be reduced to one lane and Fuller Street will be closed.

Week of July 24, 2017:

  *   Corporation Street will be reduced to one lane as waterline installation begins.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Flaggers will be utilized for traffic control.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Fuller Street will be reduced to one lane as waterline installation begins.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Flaggers will be utilized for traffic control.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Liggett Street sewer line will be inspected.
     *   Flaggers will be utilized for traffic control.
     *   No water or sewer service disruptions are anticipated.
     *   Residents and business owners will be contacted about assisting with dye testing of sewer service connections.

Saturday - Sunday July 29-30, 2017:

  *   No work planned. Corporation Street will be reduced to one lane and Fuller Street will be closed.

Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.durhamoperationgreenlight.org_&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=P9cuE7s58z3AiHwHk-252uyd7ISyrXIibBEhpubjVjI&e=>.  Find more information about all of the department's current projects at www.DurhamWaterProjects.org<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.durhamwaterprojects.org_&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=a_TY6hAafgEez5UiOC9Jftqc8r7uKu_HvyBR48S1r2Y&e=>.  If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170714/f8fe2ea2/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 2734 bytes
Desc: image001.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170714/f8fe2ea2/attachment-0001.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 23964 bytes
Desc: image002.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170714/f8fe2ea2/attachment-0001.png>


More information about the INC-list mailing list