[Durham INC] Road Closure Info & East Main Street Waterline Replacement Project Update | 8-17-17
Butts, Kirk
Kirk.Butts at durhamnc.gov
Thu Aug 17 14:42:56 EDT 2017
[cid:image001.jpg at 01D087F9.E3A39760][cid:image002.png at 01D087F9.E3A39760]
East Main Street Waterline Replacement Project Update and Two-Week Look Ahead
August 17, 2017
Improvements to the City's waterline infrastructure will continue along the East Main Street corridor. Additional information regarding this project can be found at: http://durhamnc.gov/3001/East-Main-Street-Waterline-Replacement.
Planned Road / Lane Closures will occur as follows:
* Friday, August 18th through Monday, August 21st:
* Full vehicular and pedestrian closure of the East Main Street and Fayetteville Street intersection (see attached map).
* Week of 8/21:
* Lane shifts and flaggers on East Main Street between Roxboro Street and Fayetteville Street, Hood Street, and South Elizabeth Street.
* Lane closures on Angier Avenue between East Main Street and Elm Street.
* Week of 8/28:
* Lane shifts and flaggers on East Main Street between Roxboro Street and Fayetteville Street, Hood Street, and South Elizabeth Street.
* Lane closures on Angier Avenue between East Main Street and Elm Street.
Monday through Friday August 18-21, 2017 (see attached map):
* A full vehicular and pedestrian closure of the East Main Street and Fayetteville Street intersection will be in place from 6 AM on Friday, August 18th through 8 PM on Monday, August 21st for intersection pavement improvements.
* Traffic control signs and markings will be used for East Main Street and Fayetteville / Elizabeth Street detours (see attached map).
* Noise levels in excess of the current City noise ordinance are anticipated throughout the planned closure.
* Access to businesses and residences will be maintained throughout the work.
Week of August 21, 2017:
* Sidewalk/curb replacements and abandonment of existing waterlines in East Main Street between Roxboro and Fayetteville streets, Hood Street, South Elizabeth Street, and Ramseur Street will continue.
* Lane shifts and flaggers will be used to maintain traffic at isolated locations in the project area.
* Through traffic on East Main Street will be maintained.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Stormwater installation will continue on East Main Street between South Elizabeth and Hood streets.
* Lane shifts and flaggers will be used to maintain traffic at stormwater crossing locations on East Main Street.
* Through traffic on East Main Street will be maintained.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Waterline service reconnections in Angier Avenue between East Main Street and Elm Avenue will take place.
* Service switchovers will be coordinated with each affected customer 7 days in advance of work taking place.
* An eastbound lane closure on Angier Avenue will be required to complete the work. On-street parking will be closed in the vicinity of the work.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Saturday-Sunday August 26-27, 2017:
* No work is planned for Saturday, August 26th or Sunday, August 27th.
Week of August 28, 2017:
* Sidewalk/curb replacements and abandonment of existing waterlines in East Main Street between Roxboro and Fayetteville streets, Hood Street, South Elizabeth Street, and Ramseur Street will continue.
* Lane shifts and flaggers will be used to maintain traffic at isolated locations in the project area.
* Through traffic on East Main Street will be maintained.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
* Waterline service reconnections in Angier Avenue between East Main Street and Elm Avenue will take place.
* Service switchovers will be coordinated with each affected customer 7 days in advance of work taking place.
* An eastbound lane closure on Angier Avenue will be required to complete the work. On-street parking will be closed in the vicinity of the work.
* Noise levels in excess of the current City noise ordinance are anticipated during work hours.
* Pedestrian and driveway access to buildings / facilities will be maintained at all times.
Saturday-Monday September 2-4, 2017:
* No work is planned for Saturday, September 2nd through Monday, September 4th.
Future Weeks:
* Restoration of sidewalks and other surfaces impacted by the project will continue.
* Work will exceed the current City noise ordinance.
* Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<http://www.DurhamOperationGreenlight.org>. Find more information about all of the department's current projects at www.DurhamWaterProjects.org<http://www.DurhamWaterProjects.org>. If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170817/1f3c00b7/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 2734 bytes
Desc: image001.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170817/1f3c00b7/attachment-0002.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 23964 bytes
Desc: image002.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170817/1f3c00b7/attachment-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: E Main and Fayetteville Detour 11x17 2017_08_09.jpg
Type: image/jpeg
Size: 776175 bytes
Desc: E Main and Fayetteville Detour 11x17 2017_08_09.jpg
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20170817/1f3c00b7/attachment-0003.jpg>
More information about the INC-list
mailing list