East Main Street Waterline Replacement Project Update and Two-Week Look Ahead

October 12, 2017

We are nearing the end! Major construction work is complete in the East Main Street corridor. Improvements to the City's waterline infrastructure will continue.  Additional information regarding this project can be found at: http://durhamnc.gov/3001/East-Main-Street-Waterline-Replacement.

Planned Road / Lane Closures will occur as follows:

  *   Week of 10/16:
     *   Lane shifts and flaggers on East Main Street between Roxboro Street and Fayetteville Street, Hood Street, South Elizabeth Street, and Ramseur Street.
  *   Week of 10/23:
     *   Lane shifts and flaggers on East Main Street between Roxboro Street and Fayetteville Street, Hood Street, South Elizabeth Street, and Ramseur Street.

Saturday-Sunday October 14-15, 2017:

  *   No work is planned for Saturday, October 14th or Sunday, October 15th.

Week of October 16, 2017:

  *   Sidewalk/curb replacements and abandonment of existing waterlines in East Main Street between Roxboro and Fayetteville streets, Hood Street, South Elizabeth Street, and Ramseur Street will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at isolated locations in the project area.
     *   Through traffic on East Main Street will be maintained.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Sunday October 21-22, 2017:

  *   No work is planned for Saturday, October 21st or Sunday, October 22nd.

Week of October 23, 2017:

  *   Sidewalk/curb replacements and abandonment of existing waterlines in East Main Street between Roxboro and Fayetteville streets, Hood Street, South Elizabeth Street, and Ramseur Street will continue.
     *   Lane shifts and flaggers will be used to maintain traffic at isolated locations in the project area.
     *   Through traffic on East Main Street will be maintained.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Future Weeks:

  *   All remaining work associated with the waterline installation in the East Main Street vicinity is anticipated to be completed by late October.
  *   Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<http://www.DurhamOperationGreenlight.org>.  Find more information about all of the department's current projects at www.DurhamWaterProjects.org<http://www.DurhamWaterProjects.org>.  If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20171012/b283ad37/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 4710 bytes
Desc: image001.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20171012/b283ad37/attachment.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 23964 bytes
Desc: image002.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20171012/b283ad37/attachment-0001.png>


More information about the INC-list mailing list