Central Park Waterline Replacement Project Update and Two-Week Look Ahead

March 8, 2018

The City appreciates your ongoing patience with the work along the busy corridors associated with the Central Park Waterline Replacement Project.  Additional information regarding this project can be found at: http://durhamnc.gov/1251/Durham-Central-Park-Waterline-Replacement.

Planned Road / Lane Closures will occur as follows:

  *   Week of 3/12:
     *   Roney Street will be closed between Corporation Street and Central Park.
     *   Foster Street will be closed between Corporation Street and Seminary Avenue during work hours.
     *   Intersection of Foster Street & Hunt Street will be closed during work hours.


  *   Week of 3/19:
     *   Foster Street southbound will be closed between Hunt Street and Morgan Street.

Week of March 12, 2018:

  *   Roney Street will be closed as sanitary sewer line installation continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Flaggers will be utilized for traffic control.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Foster Street between Corporation Street and Seminary Avenue will be closed as water line installation continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Periodic one-lane interruptions will occur on Corporation Street between Foster Street and North Duke Street as water services are connected to the new water line.

     *   Flaggers will be utilized for traffic control.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.

  *   Periodic one-lane interruptions will occur on Liggett Street between Corporation Street and Fernway Avenue as water services are connected to the new water line.

     *   Flaggers will be utilized for traffic control.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.

Saturday - Sunday March 17-18, 2018:

     *   No work planned. Roney Street will be closed between Corporation Street and Central Park.

Week of March 19, 2018:

  *   Foster Street will be reduced to one lane as sewer line installation begins.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Periodic one-lane interruptions will occur on Corporation Street between Foster Street and North Duke Street as water services are connected to the new water line.

     *   Flaggers will be utilized for traffic control.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.

  *   Periodic one-lane interruptions will occur on Liggett Street between Corporation Street and Fernway Avenue as water services are connected to the new water line.

     *   Flaggers will be utilized for traffic control.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.

Saturday - Sunday March 24-25, 2018:

     *   No work planned.

Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.durhamoperationgreenlight.org_&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=P9cuE7s58z3AiHwHk-252uyd7ISyrXIibBEhpubjVjI&e=>.  Find more information about all of the department's current projects at www.DurhamWaterProjects.org<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.durhamwaterprojects.org_&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=a_TY6hAafgEez5UiOC9Jftqc8r7uKu_HvyBR48S1r2Y&e=>.  If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20180308/064768da/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 9001 bytes
Desc: image001.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20180308/064768da/attachment.png>


More information about the INC-list mailing list