Central Park Waterline Replacement Project Update and Two-Week Look Ahead

February 7, 2019

The City appreciates your ongoing patience with the work along the busy corridors associated with the Central Park Waterline Replacement Project.  Additional information regarding this project can be found at: http://durhamnc.gov/1251/Durham-Central-Park-Waterline-Replacement.

Planned Road / Lane Closures will occur as follows:


  *   Week of 2/11:
     *   Intersection of Rigsbee Avenue and Seminary Avenue will be closed.
     *   Rigsbee Avenue will be reduced to one lane northbound between West Morgan Street and Hunt Street.
     *   Intersection of Foster Street and Seminary Avenue will be temporarily closed as sanitary sewer work continues.
     *   Geer Street will be reduced to one lane between Washington Street and Foster Street.
     *   Washington Street between Monmouth Avenue and Trinity Avenue will be reduced to one lane northbound as water line installation begins.
     *   The intersection of Washington Street and Monmouth Avenue will be temporarily closed as water line installation begins.
     *   Washington Street between Geer Street and West Corporation Street will be closed as sanitary sewer work begins.



  *   Week of 2/18:
     *   Intersection of Rigsbee Avenue and Seminary Avenue will be closed.
     *   Rigsbee Avenue will be reduced to one lane northbound between West Morgan Street and Hunt Street.
     *   Intersection of Foster Street and Seminary Avenue will be temporarily closed as sanitary sewer work continues.
     *   Geer Street will be reduced to one lane between Washington Street and Foster Street.
     *   Washington Street between Monmouth Avenue and Trinity Avenue will be reduced to one lane northbound as water line installation continues.
     *   Washington Street between Geer Street and West Corporation Street will be closed as sanitary sewer work continues.

Week of February 11, 2019:


  *   Rigsbee Avenue will be reduced to one lane as sanitary sewer work continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.

  *   Foster Street at Seminary Avenue will be reduced to one lane as sanitary sewer work continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.

  *   Geer Street will be reduced to one lane as sanitary sewer work continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Washington Street at Monmouth Avenue will be temporarily closed as water line work continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Washington Street between Monmouth Avenue and West Trinity Street will be reduced to one lane as water line work begins.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Washington Street between West Corporation Street and Geer Street will be closed as sanitary sewer work begins.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

Saturday - Sunday February 16-17, 2019:

     *   No work is scheduled for this weekend.

Week of February 18, 2019:


  *   Rigsbee Avenue will be reduced to one lane as water line work continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.

  *   Foster Street at Seminary Avenue will be reduced to one lane as sanitary sewer work continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.

  *   Geer Street will be reduced to one lane as sanitary sewer work continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Washington Street between Monmouth Avenue and West Trinity Street will be reduced to one lane as water line work continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Washington Street between West Corporation Street and Geer Street will be closed as sanitary sewer work begins.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

Saturday - Sunday February 23-24, 2019:

     *   No work is scheduled for this weekend.

Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.durhamoperationgreenlight.org_&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=P9cuE7s58z3AiHwHk-252uyd7ISyrXIibBEhpubjVjI&e=>.  Find more information about all of the department's current projects at www.DurhamWaterProjects.org<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.durhamwaterprojects.org_&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=a_TY6hAafgEez5UiOC9Jftqc8r7uKu_HvyBR48S1r2Y&e=>.  If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20190207/8af0a881/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 9001 bytes
Desc: image001.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20190207/8af0a881/attachment.png>


More information about the INC-list mailing list