[Durham INC] UPDATE/CORRECTION - Central Park Waterline Replacement Project | 4-12-18

Butts, Kirk Kirk.Butts at durhamnc.gov
Thu Apr 12 18:04:03 EDT 2018


[cid:e6c6caf1-2a75-414e-b0dd-ecfc82a2b0b9]



Central Park Waterline Replacement Project Update and Two-Week Look Ahead



April 12, 2018


PLEASE NOTE - Seminary Avenue will be closed between Foster Street and Rigsbee Avenue, not Foster and North Duke as stated at 4:21 p.m.


The City appreciates your ongoing patience with the work along the busy corridors associated with the Central Park Waterline Replacement Project.  Additional information regarding this project can be found at: http://durhamnc.gov/1251/Durham-Central-Park-Waterline-Replacement.



Planned Road / Lane Closures will occur as follows:

  *   Week of 4/16:
     *   Foster Street southbound will be closed between Hunt Street and Morgan Street.
     *   Intersection of Foster Street and Seminary Avenue will be closed.
     *   Seminary Avenue will be closed between Foster Street and Rigsbee Avenue.
     *   Liggett Street, Fuller Street, Corporation Street between North Duke and Foster Street, and Foster Street between Corporation Street and W Morgan Street may be closed temporarily for milling and repaving as equipment becomes available.



  *   Week of 4/23:
     *   Foster Street southbound will be closed between Hunt Street and Morgan Street.
     *   Intersection of Foster Street and Seminary Avenue will be closed.
     *   Seminary Avenue will be closed between Foster Street and Rigsbee Avenue.
     *   Liggett Street, Fuller Street, Corporation Street between North Duke and Foster Street, and Foster Street between Corporation Street and W Morgan Street may be closed temporarily for milling and repaving as equipment becomes available.



Week of April 16, 2018:

  *   Foster Street will be reduced to one lane as water line installation continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Seminary Avenue will be closed as sewer line installation begins.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.

  *   Periodic one-lane interruptions will occur on Liggett Street between Corporation Street and Fernway Avenue as water services are connected to the new water line.

     *   Flaggers will be utilized for traffic control.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.

  *   Periodic one-lane interruptions will occur on Corporation Street between Foster Street and North Duke Street as water services are connected to the new water line.

     *   Flaggers will be utilized for traffic control.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.



Saturday – Sunday April 21-22, 2018:

     *   No work planned.



Week of April 23, 2018:

  *   Foster Street will be reduced to one lane as sewer line installation continues.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   No water or sewer service disruptions are anticipated.

  *   Seminary Avenue will be closed as sewer line installation begins.

     *   Traffic control signs and markings will be used for all traffic detours.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.

  *   Periodic one-lane interruptions will occur on Corporation Street between Foster Street and North Duke Street as water services are connected to the new water line.

     *   Flaggers will be utilized for traffic control.
     *   Sidewalk traffic will be disrupted.
     *   Noise levels in excess of the current City noise ordinance are anticipated during work hours.
     *   On-street parking will be closed in work areas.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.
  *   Residents and business owners on Hunt Street between Mangum Street and Rigsbee Avenue may be contacted about testing for sanitary sewer connections.
     *   Planned work hours are 7 AM to 6 PM.
     *   Residents and business owners will be contacted in advance of any service disruptions.



Saturday – Sunday April 28-29, 2018:

     *   No work planned.



Additional information regarding this work can be found at www.DurhamOperationGreenlight.org<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.durhamoperationgreenlight.org_&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=P9cuE7s58z3AiHwHk-252uyd7ISyrXIibBEhpubjVjI&e=>.  Find more information about all of the department’s current projects at www.DurhamWaterProjects.org<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.durhamwaterprojects.org_&d=DwMFAg&c=NpiPIT1KNSO0vXgGk6ogJQ&r=z5Oe-bOyirROnWsSt-ksUmkl3gUxAJrJe3KmPML2Wjg&m=cerd20hMRjc3Lj48I0V-b_N833IineSusQFH5Y3bGIc&s=a_TY6hAafgEez5UiOC9Jftqc8r7uKu_HvyBR48S1r2Y&e=>.  If you have questions, please email DowntownLoopWRP at DurhamNC.gov<mailto:DowntownLoopWRP at DurhamNC.gov>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20180412/e3f4f8b6/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: pastedImage.png
Type: image/png
Size: 12274 bytes
Desc: pastedImage.png
URL: <http://lists.deltaforce.net/pipermail/inc-list/attachments/20180412/e3f4f8b6/attachment.png>


More information about the INC-list mailing list